Project Tasks Design

The project aims to fast-track Carrizo PSH licensing and permitting by conducting market analysis, geotechnical site investigations, tunneling and excavation planning, environmental permitting, and interconnection feasibility studies.

1. Investment Risk Reduction

  • Conduct geotechnical site investigation.
  • Evaluation of reservoir and abutment integrity.
  • Tunneling and excavation planning.
  • Preliminary powerhouse design.
  • Transmission feasibility study.

2. Project Tasks to Mitigate Market Uncertainties

  • Analyze the revenue potential and market impact of Carrizo PSH in the WECC region using market simulation tools.
  • Optimize the configuration of turbine technologies.

3. Value Proposition

  • Analyze transmission benefits of dual functions of Carrizo PSH.
  • Evaluate Carrizo PSH’s impact on system reliability and resilience under various scenarios, including extreme weather events.
  • Assess how Carrizo PSH can mitigate the variability and uncertainty of renewable energy and integrate renewable in the Navajo Nation.

 

4. Licensing and Permitting Studies

  • Interconnection studies.
  • Environmental impact studies.
  • Water right and management.
  • Land security.
  • Historic and cultural preservation.